Accelevation Solutions: Cloud computing data hall delivered in record time

Feb 11, 2025

The Challenge: A cloud computing data center needed to commission 28 pods with full containment, structure and power, but had a mere month to get it done.

The Solution:  Accelevation drew upon our geo-dispersed installation technicians and leveraged our in-house manufacturing to ship, stage, install and fit-up.  Working around holidays, the teams rapidly installed structure, containment and sealing and coordinated with structured cabling, electrical fit-out and rack installation.

  • Week 1: Structure and containment rushed to the site.   2 full installation crews were deployed to the site.  Working from opposite ends of the data hall, these technicians set steel, installed panels, and assembled HAC doors for each rack
  • Week 2: Low-voltage technicians deployed to set conveyance and run fiber, working behind the install techs
  • Week 3: Electricians began power fit-out and testing
  • Week 4: All teams finished up and certified their work for hand-off

The Result: Thanks to our national pool of installers, low-voltage techs, and electricians backed by robust project management, Accelevation delivered 28 turn-key pods in record time.