Accelevation Solutions: Cloud computing data hall delivered in record time
Feb 11, 2025The Challenge: A cloud computing data center needed to commission 28 pods with full containment, structure and power, but had a mere month to get it done.
The Solution: Accelevation drew upon our geo-dispersed installation technicians and leveraged our in-house manufacturing to ship, stage, install and fit-up. Working around holidays, the teams rapidly installed structure, containment and sealing and coordinated with structured cabling, electrical fit-out and rack installation.
- Week 1: Structure and containment rushed to the site. 2 full installation crews were deployed to the site. Working from opposite ends of the data hall, these technicians set steel, installed panels, and assembled HAC doors for each rack
- Week 2: Low-voltage technicians deployed to set conveyance and run fiber, working behind the install techs
- Week 3: Electricians began power fit-out and testing
- Week 4: All teams finished up and certified their work for hand-off
The Result: Thanks to our national pool of installers, low-voltage techs, and electricians backed by robust project management, Accelevation delivered 28 turn-key pods in record time.